Affordable Housing - Sept 2017

Construction to the 10 freehold homes within the second phase of our Crystal Park development in Benoni is progressing well. We have experienced brisk sales on site and hope to have all homes sold before the occupation date of 1 December 2017.

The final finishes are being applied to our 176 unit Brentwood development in Cosmo City. We have released the first 48 completed apartments and they were all occupied on the 1st of August. The remaining 128 units will be ready for occupation from the end of this month.  This development brought quality housing set within a safe environment to a market in dire need of such. We are already scouting for other opportunities within Cosmo City on which to develop more housing for this unsaturated market. 


05 Sep 2017
Author Renico Construction